Geothermal energy has remained largely underdeveloped and underutilized in
Indonesia, despite the many advantages it has to offer compared to currently
widely used types of energy like oil, gas and coal.

Indonesia, however, needs to come up with fiscal incentives to turn these
comparative advantages for geothermal into a significant contribution to the
government's plan to build by 2019 power plants to produce 35,000 megawatts
of electricity.

Under the 2014 National Energy Policy, renewable energy must contribute up
to 23 percent of Indonesia's overall energy mix by 2025. Geothermal
currently accounts for a small part of that mix, a mere 1,493.5 MW. The
government plans to bring this up to 7,000 MW by 2025, which means building
at a rate of 550 MW a year.

Geothermal power plants are environmentally sustainable. They leave no
carbon footprint, and the only waste comes in the form of hot water and a
tiny amount of hydrogen sulfide, which is injected back into the reservoir
as substitute fluids.

Unlike oil, gas or coal, the environmental contamination from geothermal
exploration and exploitation is negligible. Given the nature of geothermal -
fluids and hot steam - it is a source of energy that can only be used for
local power generation, not for exports.

The targeted 5,500 MW of additional geothermal capacity by 2025, if
achieved, will represent a significant cut in carbon dioxide emissions, the
equivalent emissions from 38 million tons of coal or 25 million tons of
petroleum. It will replace 88 million barrels of petroleum or 13 million
tons of coal that Indonesia burns each year. In monetary terms, this will be
a saving of $4.5 billion currently spent on petroleum or $1.5 billion on
coal every year.

Geothermal therefore plays an important role in reducing Indonesia's
dependence on fossil fuels.

Where then is the comparative disadvantage that has hampered the development
of geothermal energy?

Well-drilling exploration and development represent the biggest risks in
this business. No financial institutions in Indonesia offer funding for
geothermal exploration.

In countries like Iceland, Germany and many in East Africa aided by the
World Bank and France, geothermal companies enjoy the support of an
exploration insurance scheme. Other countries offer incentives for clean
energy development.

Indonesia should follow these examples.

Three state-owned enterprises - oil and gas company Pertamina, geothermal
power producer PT Geo Dipa Energi and power company PLN - have been assigned
to tap and build geothermal power facilities in the country.

In 2011, the Finance Ministry set up the Geothermal Fund Facility (GFF) to
be managed by state-owned infrastructure financing company PT Sarana Multi
Infrastruktur (SMI) to help accelerate geothermal energy development.

The House of Representatives followed suit by approving a line item of Rp 1
trillion annually for the GFF between 2011 and 2013. The fund, however, has
remained largely unspent because of uncertainties and risks in the absence
of insurance cover. An insurance scheme for geothermal exploration would not
only mitigate the risks from drilling failures, but it could also cut
project financing costs.

Many countries have developed geothermal facilities by mitigating the risks
of exploration through financial and fiscal incentives provided by their
governments. They include loan guarantees, partial collateral costs for
drilling failures, an insurance program to support the costs of exploration,
a tax deduction on the construction of geothermal facilities and a guarantee
of energy sales at attractive prices.

The yearly Rp 1 trillion set aside for the GFF in 2011 to 2013 could be
revived, but it would only be effective if we had an insurance scheme in
place.

What is the risk, exactly?

Published data on drilling of 300 geothermal wells show a 75 percent
success ratio, each with a production capacity of more than 7 MW. This
compares with an average success ratio of 7 to 10 percent in hydrocarbon
drilling in Indonesia.

But even wells with generating capacity of less than 5 MW are still
economically viable and can be built in areas where the market is small.

Insurers need more data and information to gain a better understanding of
exploration risks. They need to have access to geology feasibility studies,
interpretations of seismic investigations, the concept of enterprise
development, the design of the well location and well-stimulation programs.
They need to have knowledge about the development of a geothermal power
plant, the licenses involved and information about contractors and vendors,
including their directors, and independent experts responsible for
developing the proposal.

Unlike fossil fuels, developing renewable energy resources, including
geothermal, could apply for concessionary loans from developed countries
under the "Low Carbon, low CO2 emissions" scheme.

The next step would be to bring the Financial Services Authority (OJK) into
the picture to help define terms and conditions along with technical
actuarial calculations to set insurance premium rates.

As geothermal wells are all onshore, unlike oil and gas where exploration is
now concentrated mostly offshore, an insurance scheme could cover the
government's GFF.

With more than 150 volcanoes, of which 127 are active, Indonesia has an
abundance of geothermal reserves waiting to be tapped.

It is a source of energy that has many comparative advantages, in various
respects, from environmental conservation to costs. The one small
disadvantage, the absence of an insurance scheme, is something that can be
overcome.

The time is ripe for Indonesia to unleash the true energy of the Pacific
Ring of Fire.

--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---

Link to Original Article:
http://www.thejakartapost.com/news/2016/11/11/quest-insurance-scheme-ri-s-ge
othermal-future.html


--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---

John Diecker
APT Consulting Group Co., Ltd.

www.aptthailand.com

No comments:

Post a Comment

Note: Only a member of this blog may post a comment.