Philippines: DENR's audit on coal plants now ongoing
The Department of Environment and Natural Resources (DENR) has already begun
its audit of all coal-fired power plants in the country which involves the
evaluation of their environmental compliance certificates (ECCs).
"So far, two coal plants have been audited ahead of the audit guidelines. We
have seen exceedance of different nature in both audits. I will reveal [the
specific plants] when all plants have been audited already," Environment
Undersecretary for Legal Affairs Maria Paz Luna told reporters on Monday,
November 21.
She further explained that they will select the 25 most critical environment
projects based on complaints received by the DENR, and whether the project
might cause irreparable damage to the environment. The department will audit
those projects first.
"Any conditions that remain unfulfilled with the ECC will result in a
suspension of the ECC if they can't comply with the condition," Luna added.
Environment Secretary Gina Lopez said "it doesn't make sense at all to have
any more coal plants." (READ: Lopez: Clean energy is the way to go)
"I've had 4 studies on coal plants done with two gentlemen with doctorate
degrees and in the 4 studies, the people's health suffered, agriculture
suffered, and fishery resource suffered. The economy suffered. And I kept
thinking, that's why coal is cheap, because the company doesn't pay for the
negative externalities," she explained on Tuesday.
She noted that the cost of renewable energy is already going down, and may
even be cheaper then coal in 5 years' time.
"What happens with coal is when you agree with coal, you're stuck with it
for 25 years. And if the price of solar goes down and other renewables go
down – and it's better to go to renewables because it's cheaper – then that
coal becomes a liability because the government has to continue to pay for
25 years to sign the contract."
She believes it makes "much more economic and benevolent sense" to run the
country's economy on "what we have, which is wind, solar, geothermal" energy
since the Philippines, she said, is not an industrial country.
"We have to gravitate towards a situation where renewable can adopt
baseloads. So I want to be able to do that in the convergence areas of
DENR," Lopez added.
President Rodrigo Duterte was initially hesitant about the Paris Agreement
on Climate Change because he believes addressing global warming should not
stymie the Philippines' bid to industrialize.
Under the agreement, countries agreed to keep global temperature rise this
century to below 2°C, with the aim of containing it below 1.5ºC, above
pre-Industrial Revolution levels, by cutting greenhouse gas emissions.
The Philippines pledged to cut by 70% its carbon emissions by 2030 – a
target conditional on assistance from the international community.
Duterte eventually agreed to sign the Paris agreement after he was persuaded
by his Cabinet. Lopez said she expects it to be ratified by the country this
year.
The landmark international climate pact already came into force this month.
During the recently concluded world climate conference, COP22, in Morocco,
Lopez got to talk to other countries such as Germany and France about
renewable energy.
The environment department already has initial plans to go renewable in at
least 3 areas: Sorsogon, Palawan, and Guimaras.
--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---
Link to Original Article:
http://www.rappler.com/nation/153201-philippines-denr-audit-coal-plants
--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---
John Diecker
APT Consulting Group Co., Ltd.
www.aptthailand.com
No comments:
Post a Comment
Note: Only a member of this blog may post a comment.