Myanmar: Coal power station given trial run

Myanmar: Coal power station given trial run

A one-month test run of Tikyit coal-fired power station has been granted by
the Shan State government and the Ministry of Electric Power and Energy, the
project chief Win Htay told the Daily Eleven.

The station has been idle for about two years.

"We cannot run it immediately after repairing the generator. We have to make
trial tests step by step," he said.

The ministry granted the Chinese company Wuxi Hua Guang Electric Power
Engineering Co Ltd the contract to run the plant under a long-term agreement
last November.

"We instructed the company to guarantee international standards. We will
know whether they can follow the rules after running trial tests. We told
them we will monitor the trial test with technicians and submit the results
to the government for a decision," said Win Htay.

Now the company is cleaning two boilers.

The Myanmar Investment Commission granted the Tikyi contract to the Chinese
company last November.

--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---