Indonesia's PLN signs deals for 45 MW of solar
State-owned utility PT PLN (Persero) signed agreements with six developers
in late March to build PV projects throughout the Southeast Asian nation.
Infrastruktur Terbarukan Lestari is set to build the biggest of the
projects, after signing a heads of agreement for the development of 15 MW in
Minahasa, North Sulawesi province, according to a statement from the
Ministry of Energy and Mineral Resources (ESDM).
PT Quantum Energy - an independent power producer that first signed a
memorandum of understanding (MoU) with PLN in late 2015 to build up to 100
MW of utility-scale PV in Indonesia - has signed a heads of agreement to
install 10 MW in Gorontalo province, also on the island of Sulawesi.
Meanwhile, PT Infrastruktur Terbarukan Adhiguna, PT Infrastruktur Terbarukan
Cemerlang, PT Infrastruktur Terbarukan Buana and PT Delapan Menit Energi
have all expressed interest in developing 5 MW projects on the island of
Lombok, in West Nusa Tenggara province.
PLN has not published the tariff for the projects, and it is not yet clear
whether these projects will be built with the old FITs or with the new
reduced FITs, since the law changed recently. The ESDM did not say when the
developers would launch feasibility studies for the six projects.
PLN also recently signed MoUs for the development of hybrid solar, wind and
hydropower projects with the Indonesian unit of China's UPC Renewables on
Sulawesi and the Maluku Islands. The Jakarta-based utility also signed deals
with several other developers to build a number of PV+diesel hybrid plants
on the islands of Sumatra and Java, but the ESDM did not disclose additional
details.
PLN has been unwilling to connect new PV projects online, and it is unclear
in the new law if it can induce PV investment. Therefore, many investors
have instead turned to offgrid projects, which often favors Indonesia's
geography. Again, most of these PV projects are MoUs and Indonesia's
government will need to find ways to facilitate their development.
In late January, the ESDM announced new regulations to back the development
of renewable energy, replacing the original feed-in tariff (FIT) system that
was introduced in 2009.
PLN is now expected to launch tenders for solar and wind projects, based on
its capacity quotas. Purchase-price ceilings have been set for PV-generated
electricity, to be determined according to the utility's cost of generation,
which varies by geographic location.
In July 2016, Indonesian government set a 250 MW solar build-out quota, as
the first step toward eventually developing 5 GW of capacity. However, the
feasibility of the target has been thrown into doubt in recent months by
government in-fighting and confusing policy signals.
Despite this, numerous developers - frustrated by the government's lack of
clarity on solar - have directly negotiated power purchase agreements with
PLN, outside of any government support scheme.
Most recently, France's Engie announced plans to invest up to $1 billion in
500 MW of PV and biomass capacity with PT Sugar Group over the next five
years. Engie also agreed to invest up to $240 million in PV-powered
microgrid projects in Papua with microgrid developer Electric Vine
Industries, in addition to plans to invest $15 million in the development of
solar projects in East Nusa Tenggara province with PT Arya Watala Capital.
Jakarta has said that it wants renewables to account for 23% of Indonesia's
energy mix by 2025, with the ESDM estimating last year that solar could
account for 6.4 GW of total renewables build-out over the next eight years.
However, the country's total installed PV capacity remains negligible, at
just 12 MW by the end of 2015, according to the International Renewable
Energy Agency (IRENA).
--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---
Link to Original Article:
https://www.pv-magazine.com/2017/04/10/indonesias-pln-signs-deals-for-45-mw-