Vietnam: EVN working to power up the south
Due to a power source imbalance, the southern region of Vietnam will be at
risk of power shortages from 2018 on, while thermal power projects not
managed by Vietnam Electricity (EVN) are lagging behind schedule. Therefore,
EVN is seeking solutions to the problem.
Rising demand
According to an EVN report, during the 2017-2020 period, the national power
system will still maintain a crude reserve capacity of over 30 percent.
However, the allocation of power sources among regions is not even, with
most of them located in the north and central provinces. The south gets its
power through a transmission system. With a higher growth rate compared to
the national average, power shortages in the south will not only directly
affect industrial and agricultural production, exports and foreign
investment attraction, but also slow down socio-economic development.
Ngo Son Hai, deputy general director of EVN, said the southern region
currently has some operating coal and gas-fired power plants, while others
are under construction. In addition to local power sources, the region needs
about 15 billion kWh of electricity by 2017 and 21 billion kWh of
electricity by 2019 through the transmission system. However, this system
only provides about 18.5 billion kWh of electricity a year and is under
great pressure due to large and continuous transmission.
To ensure sufficient power supplies for the south, EVN has invested in the
development of power sources according to the National Power Development
Planning for the 2011-2020 period, with a vision to 2030 (Power Planning
VII), such as expanding coal-fired power plants in Binh Thuan Province's
Vinh Tan Power Center and Tra Vinh Province's Duyen Hai Power Center, and
developing renewable energy projects.
EVN has also invested in the development of various power transmission
projects, such as the Vung Ang-Doc Soi-Pleiku 500kV transmission line. After
these projects are put into operation, capacity could increase by 5.5
billion kWh of electricity a year in the northern-central transmission
system, and about 2.5-3.6 billion kWh of electricity a year in the
central-southern transmission system.
Accelerating progress
The development of power sources managed by EVN in the south has basically
been on schedule. However, the group is urging units to further speed up the
progress in order to ensure sufficient power supplies for the south.
According to the plan, the national power system still guarantees supplies
for the south in 2017 thanks to local power plants and the transmission
system. However, power transmission is very risky, while hydropower plants
are constrained by water resources and new thermal power plants take three
to five years to be stable.
Vu Ngoc Minh, the general director of the National Power Transmission
Corporation, said that the corporation is preparing for the construction of
the Vung Ang-Quang Trach-Doc Soi-Pleiku 2 500kV triple circuit transmission
line at the end of this year. However ground clearance is the most difficult
problem in this project.
Nguyen Phuoc Duc, the deputy general director of EVN's Southern Power
Corporation, said that to meet the load demand of about 14 percent, it is
necessary to accelerate the construction and put into operation the Can Tho
and Tay Ninh 2 220kV transformer stations. In addition, the corporation will
take the initiative in maximizing capacity from small hydropower projects in
the provinces of Lam Dong, Ninh Thuan, Binh Phuoc, Ba Ria-Vung Tau, Soc
Trang and Tay Ninh to ensure power supplies for the south.
On the actual survey of Soc Trang Province's Long Phu 1 Thermal Power Plant
and Hau Giang Province's Song Hau 1 Thermal Power Plant, Deputy Prime
Minister Trinh Dinh Dung said that power plant projects are facing risks of
lagging behind schedule. Therefore, solutions to resolve difficulties for
investors are required.
Regarding coal ports, if the Vietnam National Coal-Mineral Industries
Holding Corporation Limited cannot carry out the projects, it needs to call
for more investors, including private ones.
--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---
Link to Original Article:
http://nangluongvietnam.vn/news/en/electricity/evn-working-to-power-up-the-s
outh.html
--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---
John Diecker