Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been successful implemented

Pressure test of boiler No 2 of Thai Binh 2 Thermal Power Plant has been
successful implemented

The Vietnam Lilama Corporation has successfully implemented high pressure
test of boiler No2 of Thai Binh 2 Thermal Power Plant under witness and
control of the experts from PetroVietnam.

Investor, EPC contractor, American Society of Mechanical Engineers (ASME),
MOIT and PetroVietnam Technical Safety Registration Company Ltd (PVEIC-TSR).

Previously, on August 13, 2016 Lilama already successfully implemented low
pressure test of the boiler No2: all the welds and structures of the boiler
has met technical parameters when test pressure increasing up to 295
bar(g)/(302kg/cm2).

The successful pressure test of boiler No2 is an important milestone marking
the perfection of pressure -mechanical component executing work boiler and
the construction progress of the plant.

After the pressure test, Lilama will continue to improve the rest parts of
the unit No2 and with a goal to put the whole plant into test operation in
the first quarter of 2017 as the planned schedule.

In July 2016, Lilama already implemented successfully the pressure test of
boiler No1 with meeting the designed technical parameters.

Thai Binh 2 Thermal Power Plant has a capacity of 1200MW (2x600 MW) and a
total investment level of over VND 34,295 billion ($ 1.7 billion). The plant
invested by PetroVietnam, will be operated by PVN&EVN combination and use
domestic coal of Vinacomin.

--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---

Link to Original Article:
http://nangluongvietnam.vn/news/en/electricity/pressure-test-of-boiler-no-2-
of-thai-binh-2-thermal-power-plant-has-been-successful-implemented.html


--- --- --- --- --- --- --- --- --- --- --- --- --- --- ---